Building to the Future Homes Standard (FHS) requires developers to rethink procurement, construction methods, and commercial planning. The additional build cost of 3–5% over current Part L 2021 compliance is driven primarily by heat pump installation, mandatory solar PV, MVHR, and enhanced fabric performance. This guide provides a detailed cost breakdown, transitional strategy options, procurement advice for key components, and a risk management framework to help developers navigate the transition from Part L 2021 to the FHS.
Detailed Cost Analysis
The cost of FHS compliance varies significantly by house type, construction method, and volume. The figures below are based on industry estimates for a typical 3-bedroom detached house, comparing the additional cost over current Part L 2021 compliance:
Heating System
The shift from gas boilers to heat pumps is the single largest cost increase. However, gas infrastructure savings (no gas main connection, no gas pipework within the dwelling) partially offset the heat pump cost:
| Item | Part L 2021 Cost | FHS Cost | Net Additional |
|---|---|---|---|
| Heating appliance | Gas boiler: £1,500–2,500 | ASHP: £5,000–8,000 | +£3,500–5,500 |
| Hot water storage | None (combi) or £300–500 | Cylinder: £500–800 | +£0–500 |
| Gas main connection | £500–1,500 per plot | Not required | −£500–1,500 |
| Internal gas pipework | £200–400 | Not required | −£200–400 |
| Heat emitters | Standard radiators: £800–1,200 | Oversized rads or UFH: £1,500–3,000 | +£700–1,800 |
Solar PV
The FHS requires solar PV on most new homes, with a target of 40% coverage of the building's floor area. For a typical 3-bedroom home, this translates to approximately 3–4 kWp of installed capacity:
- Panels and inverter: £3,000–4,500
- Installation: £1,000–1,500 (integrated with roof construction reduces scaffolding costs)
- Battery storage (optional): £2,000–4,000 for a 5–10 kWh unit — not required but improves self-consumption and buyer appeal
At volume, solar PV costs are falling rapidly. Developers installing across multiple sites can negotiate framework agreements that bring per-unit costs well below the figures above.
Fabric and Ventilation
| Element | Part L 2021 Cost | FHS Cost | Net Additional |
|---|---|---|---|
| Windows (3-bed) | Double glazing: £3,000–5,000 | Triple glazing: £4,500–8,000 | +£1,500–3,000 |
| Wall insulation | Standard cavity or timber frame | Enhanced thickness/specification | +£500–1,000 |
| Roof insulation | Standard loft/rafter insulation | Enhanced specification | +£200–500 |
| Floor insulation | Standard PIR below slab | Enhanced thickness | +£200–500 |
| Ventilation system | MEV or trickle vents: £300–500 | MVHR system: £3,000–5,000 | +£2,500–4,500 |
| Airtightness | Standard detailing | Enhanced detailing + testing | +£500–1,500 |
Total Additional Cost Summary
Transitional Strategy
How you approach the transition depends on the current state of your pipeline. Below are strategies for different scenarios:
Sites Already in the Planning System
- Register plots before the FHS comes into force (expected late 2026) to secure transitional eligibility
- Accelerate commencement on registered plots to start drainage and foundation work within the 12-month window
- Prioritise plot sequencing — start with plots that have the longest lead times or are most commercially sensitive
- Consider phased registration to spread the administrative burden and Building Control demand
New Sites Not Yet Registered
- Design for FHS from the outset — retrofitting FHS specifications onto a Part L 2021 design is more expensive and often compromises performance
- Engage an energy assessor early — run preliminary ECaaS calculations during design development to test compliance before committing to specifications
- Use a fabric-first approach — optimise the building envelope before relying on additional renewables or technology to close the compliance gap
- Consider compact house types with low form factors — these achieve compliance more easily and at lower cost. See our Architect Design Guide for details
Phased Developments (Mixed Regulations)
On phased sites where some plots are commenced under Part L 2021 and others must meet FHS, operational complexity increases:
- Different supply chains may run in parallel — gas boilers and gas mains for early plots, heat pumps for later plots
- Different subcontractor teams may be needed for MVHR installation, enhanced airtightness, and heat pump commissioning
- Different assessment requirements — SAP for transitional plots, HEM via ECaaS for FHS plots
- Consider standardising on FHS specifications across the entire site to simplify procurement, training, and quality control — even where transitional plots could legally use Part L 2021
Procurement Planning
As the FHS deadline approaches, demand will spike for several key components. Early procurement planning is essential to avoid shortages and price inflation:
Priority Items
| Component | Lead Time Risk | Recommended Action |
|---|---|---|
| Air source heat pumps | High — demand spike expected | Establish manufacturer framework; standardise on 1–2 models |
| MVHR units | Medium — specialist product | Agree volume supply; coordinate with duct suppliers |
| Triple-glazed windows | Medium — longer lead than double | Order early; standardise window sizes to reduce bespoke costs |
| Solar PV panels + inverters | Medium — global supply | Framework agreements; coordinate with roofing programme |
| Hot water cylinders | Low–Medium | Standardise specification; coordinate with heat pump selection |
| Skilled labour (MVHR, ASHP) | High — training pipeline limited | Invest in subcontractor training now; book installation teams early |
Standardisation Benefits
Standardising specifications across house types and sites delivers significant advantages:
- Volume discounts from heat pump, MVHR, and PV manufacturers
- Simplified training — site teams learn one heat pump installation method, one MVHR commissioning process
- Faster HEM assessments — product data (make/model from the PCDB) only needs to be gathered once per product, then reused across plots
- Reduced snagging — consistent specifications mean consistent installation quality
- Warranty simplification — fewer product variants means simpler aftercare
Risk Management
| Risk | Impact | Mitigation |
|---|---|---|
| FHS deadline shifts earlier | High — reduced transitional window | Design new sites for FHS from the outset; don't rely on transition |
| Heat pump supply shortage | High — construction delays | Framework contracts; multiple approved suppliers; early ordering |
| Skilled labour shortage | High — quality and programme risk | Invest in training; retain key subcontractors; allow programme float |
| HEM calculation fails compliance | Medium — design rework needed | Run preliminary ECaaS calculations early in design; use fabric-first approach |
| Commencement deadline missed | High — plot must meet FHS | Realistic programmes with contingency; accelerate foundations early |
| Material cost inflation | Medium — margin compression | Fixed-price contracts; early procurement; standardise specifications |
Commercial Considerations
Pricing and Sales
FHS homes offer genuine commercial advantages that can offset the additional build cost:
- Lower running costs: Energy bills 40–50% lower than conventional homes — a compelling selling point, especially during periods of high energy prices
- EPC ratings: FHS homes will achieve high EPC ratings (A or B), which are increasingly prominent in property searches and lending decisions
- Green mortgages: A growing number of lenders offer preferential mortgage rates for energy-efficient homes, improving buyer affordability
- Future-proofing: FHS homes will not need further upgrades to meet future carbon regulations, protecting resale values
- Marketing differentiation: “Zero carbon ready” is a strong marketing message that appeals to environmentally conscious buyers
Warranty and Aftercare
New technologies bring new aftercare responsibilities. Developers should plan for:
- Heat pump commissioning records — essential for warranty claims and performance verification
- MVHR commissioning and handover — homeowners need clear instructions for filter replacement, boost controls, and summer bypass operation
- Homeowner education — FHS homes operate differently from conventional homes. Invest in clear handover documentation and consider offering buyer workshops
- Defect liability — airtightness defects and heat pump performance issues may emerge after completion. Budget for post-completion testing and rectification
Developer Preparation Checklist
Frequently Asked Questions
What is the full cost breakdown for an FHS-compliant home?
The main additional costs are: heat pump + cylinder (£5,000–8,000), solar PV (£4,000–6,000), MVHR (£3,000–5,000), triple glazing premium (£1,500–3,000), enhanced insulation (£1,000–2,000), and airtightness detailing (£500–1,500). Total additional cost is estimated at 3–5% of build cost, varying by house type and volume.
What is the best transitional strategy for developers?
Register plots before the FHS comes into force (expected late 2026) to secure transitional eligibility. For plots that cannot commence within the 12-month window, plan for FHS compliance from the outset — retrofitting FHS specifications onto a Part L 2021 design is more expensive than designing for FHS from the start. Many developers are running pilot FHS-compliant schemes now to build experience.
How should developers plan heat pump procurement?
Early procurement is critical. As the FHS deadline approaches, demand for heat pumps will spike, potentially causing supply shortages and price increases. Establish relationships with manufacturers now, agree framework contracts for volume supply, and consider standardising on one or two heat pump models to simplify procurement and installation training. The same applies to MVHR units, solar PV, and triple glazing.
Do transitional arrangements apply site-wide or per plot?
Transitional arrangements operate on an individual building basis, not site-wide. Different plots on the same site may fall under different regulations. A plot registered before the FHS and commenced in time can use Part L 2021 rules, while an adjacent plot registered after the deadline must meet FHS. This creates operational complexity for phased developments. See our Transitional Arrangements page for strategies.
Will FHS homes be more attractive to buyers?
Yes. FHS homes will have energy bills 40–50% lower, better comfort from MVHR and consistent temperatures, and a strong sustainability profile. As EPC ratings become more prominent and green mortgages reward efficiency, FHS homes are expected to command a premium. The zero carbon ready designation also future-proofs against tightening carbon regulations.
Related Pages
Transitional Arrangements
Detailed guidance on plot registration deadlines, commencement definitions, and transitional strategies.
Compliance Pathways
HEM vs SAP 10.3 routes, the notional building approach, and how to demonstrate compliance.
Architect Design Guide
Form factor, glazing, thermal bridges, and design strategies for FHS compliance.
Timeline & Status
Live tracker of FHS, HEM, and EPC reform milestones and deadlines.