The Future Homes Standard (FHS) transforms on-site construction practice for new homes in England. Gas boilers are effectively replaced by heat pumps, every home needs MVHR and solar PV, airtightness targets are dramatically tighter, and insulation specifications step up to triple glazing and enhanced wall, floor, and roof U-values. These changes require new skills, new supply chains, and careful coordination between trades. This page summarises what changes on site and what builders need to prepare for.
For detailed guidance on each construction change, see our FHS Construction Changes Guide.
What Changes on Site
The table below summarises the key construction changes between current Part L 2021 homes and FHS-compliant homes:
| Element | Part L 2021 (Current) | Future Homes Standard |
|---|---|---|
| Heating | Gas boiler (combi or system) | Air source heat pump + hot water cylinder |
| Gas supply | Mains gas connection | No gas connection required |
| Ventilation | MEV, dMEV, or trickle vents | MVHR with full duct distribution |
| Windows | Double glazing (1.4–1.6 W/m²K) | Triple glazing (0.8–1.2 W/m²K) |
| Wall insulation | Standard Part L specification | Enhanced — U-value ≤ 0.15–0.18 W/m²K |
| Airtightness | ≤ 8 m³/(h·m²) @ 50 Pa (max) | Target 3 m³/(h·m²) @ 50 Pa |
| Solar PV | Not required | Mandatory — 40% floor area coverage target |
| Heat emitters | Standard radiators (70°C flow) | Oversized radiators or UFH (40°C flow) |
| Digital records | Standard handover pack | Golden Thread digital records (Building Safety Act) |
Key Construction Areas
Heat Pump Installation
Every FHS home will need a heat pump — typically an air source heat pump (ASHP) for most housing typologies. This introduces new requirements for builders:
- External unit: Concrete plinth, pipework penetrations, electrical connection, and adequate clearance for airflow
- Hot water cylinder: Internal space for a 150–250 litre cylinder (combi-style instant hot water is not compatible with heat pumps)
- Low-temperature emitters: Radiators sized for 40°C flow temperature (2–3 times larger than conventional) or underfloor heating
- Commissioning: Heat pumps require specialist commissioning — flow rates, refrigerant charge, and controller settings must all be verified
Airtightness
The FHS airtightness target of 3 m³/(h·m²) at 50 Pa requires a step change in construction quality. This level cannot be achieved through standard construction detailing alone — it requires a deliberate, continuous air barrier strategy:
- Every junction, penetration, and service route through the air barrier must be individually sealed
- Proprietary tapes, grommets, and membranes replace site-applied mastic for critical seals
- Mid-build airtightness tests are strongly recommended to catch issues before finishes are applied
- All trades must understand the air barrier location and their responsibility to maintain it
MVHR Installation
MVHR systems require dedicated duct routes from the central unit to every habitable room and wet room. For builders, this means:
- Duct installation is a first-fix activity — routes must be installed before ceilings and floor finishes
- 80–120 metres of ducting in a typical 3-bed home, requiring careful coordination with other services
- Rigid or semi-rigid ducting is preferred over flexible for performance and hygiene
- Commissioning: Airflow at every valve must be measured and balanced after completion
Solar PV
Solar PV installation must be coordinated with the roofing programme. Key considerations for builders include structural loading (12–15 kg/m²), weathertight panel mounting, DC cabling routes to the inverter location, and coordination with the electrician for grid connection.
Under HEM, solar PV is modelled very differently from SAP. Where SAP calculated annual PV generation as a single total, HEM models generation at half-hourly intervals and matches it against half-hourly household demand. This means the orientation and pitch of panels have a measurable impact on the energy rating — not just total output, but when that output occurs relative to demand.
- Orientation matters more — west-facing panels that generate during evening demand peaks may contribute more to self-consumption than south-facing panels that peak at midday when occupants are out. HEM captures this distinction; SAP could not
- Battery storage interactions — HEM can model battery charge and discharge cycles, meaning builders who install battery storage alongside PV will see this reflected in the energy rating. This opens up system design options that SAP simply ignored
- Practical installation — panels must be installed to the specified orientation and pitch. A roof-integrated system installed 20° off the design orientation will produce different results in HEM, whereas SAP would not have distinguished between them
For builders, the key takeaway is that PV installation quality and accuracy now matter for compliance, not just quantity of panels installed.
Common Mistakes That HEM Will Expose
From our experience assessing thousands of new-build properties, many common construction shortcuts that went unnoticed under SAP will become visible under HEM's more detailed modelling. These are the areas where we see the most problems on site.
Airtight Membrane Failures
The air barrier is only as good as its weakest point, and in practice most failures occur at junctions and penetrations rather than in the membrane itself:
- Unsealed service penetrations — every pipe, cable, and duct that passes through the air barrier needs an individual seal. On a typical 3-bed house, there can be 50+ service penetrations. Missing even a handful will show up in the airtightness test
- Poor tape adhesion at junctions — proprietary airtightness tapes require clean, dry surfaces and firm pressure to bond properly. In wet or dusty site conditions, tapes applied quickly without surface preparation regularly fail within weeks. Junction details between membrane sheets, around window frames, and at wall-ceiling intersections are the most common failure points
- Membrane damage from follow-on trades — electricians routing cables, plumbers installing pipework, and carpenters fixing battens all work after the air barrier is installed. Without clear marking and awareness of the air barrier location, follow-on trades regularly puncture or tear the membrane without realising it
Under HEM, airtightness has a greater impact on the overall energy rating because infiltration is modelled dynamically rather than as a fixed assumption. A building that tests at 5 m³/(h·m²) instead of the design target of 3 m³/(h·m²) will show measurably higher heating demand in the HEM output.
MVHR Duct Coordination
MVHR duct installation is one of the most coordination-intensive activities in an FHS build, and the most common source of performance problems:
- Routing conflicts — MVHR ducts compete for space with plumbing waste pipes, hot and cold water supplies, heat pump pipework, and electrical cables. Without early coordination between M&E trades, ducts end up squeezed into inadequate voids, creating excessive bends and restrictions
- Duct length and pressure drop — every metre of ductwork and every bend adds resistance. If duct runs exceed the manufacturer's specification, the MVHR unit cannot deliver the designed airflow. HEM models ventilation rates at each timestep, so an under-performing system will produce higher modelled demand
- Crushing and kinking — semi-rigid ducts routed through tight spaces or beneath heavy cable bundles get flattened, reducing airflow. This is particularly common in floor voids and ceiling spaces where ducts are installed before other services and then compressed by follow-on work
- Condensation and hygiene — poorly insulated duct runs through cold spaces (lofts, unheated voids) can develop condensation. Rigid ducting with proper insulation is strongly preferred over flexible ducting for this reason
Thermal Bridging at Junctions
HEM models thermal bridging with more granularity than SAP, using psi-values at each junction type rather than a blanket percentage addition. The common weak points are:
- Window reveals — where insulation wraps around the window opening. Insufficient return of insulation at the reveal creates a cold bridge that HEM will model as increased heat loss
- Floor-wall junctions — particularly at ground floor level where the wall insulation meets the floor insulation. A gap or misalignment between the two creates a thermal bridge running the entire perimeter of the building
- Balcony and canopy connections — structural elements that penetrate the insulation layer, such as steel balcony supports or concrete canopy slabs, create point thermal bridges that can dominate the heat loss at that junction
Commissioning Failures
Even well-installed systems can underperform if commissioning is inadequate:
- MVHR not commissioned — airflow at each supply and extract valve must be measured and balanced after installation. An uncommissioned system may deliver 30–50% less airflow than designed, leading to poor air quality and moisture problems. HEM assumes the system operates as designed — if it does not, the gap between modelled and actual performance will be significant
- Heat pumps on default settings — heat pumps must be commissioned to the specific building: flow temperatures, weather compensation curves, hot water schedules, and defrost settings all need configuring. A heat pump left on factory defaults will run less efficiently than HEM predicts, increasing energy bills for the occupant
Build Programme Implications
The FHS does not just add new technologies — it changes the sequence and coordination of the build programme. Builders who plan for these changes will avoid costly rework and delays.
Earlier Coordination Between Trades
Under current practice, M&E coordination often happens reactively — services are routed around whatever structure is already in place. Under the FHS, three systems need early coordination:
- MVHR duct routes must be designed and agreed before first fix begins. Duct paths through floor voids, ceiling spaces, and risers need to be clearly marked on drawings and protected during construction
- Heat pump pipework routes from the external unit to the cylinder and distribution system must be planned alongside the MVHR ducting, not in competition with it
- Air barrier continuity must be understood by every trade that works near or through it. This requires a clear air barrier strategy drawing that all trades can reference
Airtightness as a Whole-Team Responsibility
Achieving 3 m³/(h·m²) is not the responsibility of a single trade. Every operative who makes a penetration, fixes a bracket, or routes a service through the thermal envelope affects airtightness. Practical steps include:
- Site induction covering the air barrier location and the requirement to seal all penetrations
- Proprietary grommets and sealants available on site at all times (not ordered as an afterthought)
- Mid-build airtightness testing after the air barrier is complete but before plasterboard and finishes cover it — finding problems at this stage is far cheaper than after completion
Testing and Commissioning Requirements
FHS homes require more testing and commissioning than current Part L homes:
- Airtightness testing — mandatory, with the result feeding directly into the HEM calculation
- MVHR commissioning — measured airflow at every terminal, documented and signed off
- Heat pump commissioning — MCS-certified installation with documented flow rates, refrigerant charge, and controller configuration
- As-built SAP/HEM assessment — the energy assessor's as-built calculation must reflect what was actually constructed, not just the design intent
Building these testing and commissioning activities into the programme — rather than treating them as last-minute items before handover — is essential for FHS compliance.
Frequently Asked Questions
Will builders still install gas boilers in new homes?
No. The FHS carbon targets mean gas boilers cannot achieve compliance in new homes. All new builds will need low-carbon heating — primarily heat pumps. Gas boiler installation in new builds will cease after the transitional period ends (expected late 2027). Existing homes are not affected.
What airtightness level do FHS homes need to achieve?
The FHS notional dwelling targets 3 m³/(h·m²) at 50 Pa — significantly tighter than the current Part L maximum of 8 m³/(h·m²). This requires a continuous air barrier, careful sealing of all penetrations, and meticulous detailing. Airtightness testing remains mandatory. At this level, MVHR is essential.
Do all FHS homes need MVHR?
Not explicitly mandated, but at the FHS airtightness target of 3 m³/(h·m²), MVHR is the only practical ventilation strategy. Uncontrolled infiltration is insufficient for air quality at this level, and ventilation without heat recovery wastes the energy saved by improved airtightness. In practice, MVHR will be standard in virtually all FHS homes.
Will builders need to install solar PV on every new home?
Yes, in most cases. The government announced in June 2025 that solar panels become a functional requirement under the FHS. Developers must achieve 40% solar coverage of the floor area where feasible. Builders will need to coordinate PV installation with the roofing programme, including structural loading, panel mounting, and inverter wiring.
What new skills do builders need for FHS homes?
Key new skills include: heat pump installation and commissioning, MVHR duct installation and commissioning, enhanced airtightness construction (air barriers, penetration sealing), solar PV mounting and wiring, triple glazing installation, and digital record-keeping under the Building Safety Act. Many require specific training and certification.
How does HEM affect building site inspections?
HEM itself does not change building control inspections, but the FHS introduces higher performance requirements that will be inspected. Airtightness testing feeds directly into HEM. MVHR commissioning documents must be provided. Heat pump installation must comply with MCS standards. Inspectors are expected to place greater emphasis on junction detailing, air barrier continuity, and services coordination.
Do builders need HEM training?
Builders do not need to run HEM calculations — that is the energy assessor's role. However, site teams need to understand what HEM models and why it matters: airtightness construction techniques, MVHR duct installation best practices, heat pump system requirements, and the coordination between trades required for FHS targets. CITB and NHBC are developing FHS-specific training programmes.
What airtightness level does the Future Homes Standard require?
The FHS notional dwelling targets 3 m³/(h·m²) at 50 Pa — a significant step down from the current Part L maximum of 8 m³/(h·m²). This requires a continuous air barrier, individually sealed penetrations, proprietary tapes and membranes, and whole-team awareness. At this level, MVHR is essential for indoor air quality.
How does MVHR commissioning work under HEM?
MVHR commissioning involves measuring airflow at every supply and extract terminal using a flow hood, then adjusting valve settings until each room receives its design airflow rate. Total supply and extract must be balanced within 10%. Results are recorded on a standard form and submitted as compliance evidence. HEM assumes rated performance — an uncommissioned system will significantly underperform.
Related Pages
FHS Construction Changes Guide
Every on-site change: heat pumps, MVHR, airtightness, insulation, solar PV, and digital records.
Part L Changes
Fabric specifications, U-values, heating requirements, and the full Part L breakdown.
For Developers
Cost impact, transitional arrangements, and compliance strategy for FHS projects.
For SAP Assessors
How the transition to HEM affects energy assessment workflows and data requirements.